Below is a tentative timeline for the start of the projects that were approved on the bond and levy issues (subject to change based on weather and other factors). After continued conversations with the architect and construction manager, some of the project timelines have changed from the original schedule.
Spring 2021-Summer 2021
Design and layout for the new transportation/maintenance/District Office building is discussed. During this phase, the architect and construction manager prepares the project for bid.
Fall 2021
Grading and utility work for new transportation, maintenance, District office building begins.
Winter 2021
Construction begins for new transportation, maintenance, District office building
Summer 2022
Completion of new transportation, maintenance, District office building
Parking lot and drive improvements (Blue Hills, Fire Prairie, new bus drive, demo existing maintenance, transportation, District office buildings and replace with parking lots, OTMS parking and circle drive)
Resurface parking and drives on main campus east of Indian Lane (Career Center, OTMS)
Begin construction of new gym at the high school
Kitchen renovations at Blue Hills, Buckner, Fire Prairie and OTMS
Summer 2023
Complete new gym at the high school
High school band room expansion and remodel
Kitchen renovations at Elm Grove, Indian Trails, Cler-Mont and high school