Thank you for your support!

  • Below is a tentative timeline for the start of the projects that were approved on the bond and levy issues (subject to change based on weather and other factors). After continued conversations with the architect and construction manager, some of the project timelines have changed from the original schedule. 

    Spring 2021-Summer 2021

    • Design and layout for the new transportation/maintenance/District Office building is discussed. During this phase, the architect and construction manager prepares the project for bid. 


    Fall 2021

    • Grading and utility work for new transportation, maintenance, District office building begins.


    Winter 2021

    • Construction begins for new transportation, maintenance, District office building


    Summer 2022

    • Completion of new transportation, maintenance, District office building
    • Parking lot and drive improvements (Blue Hills, Fire Prairie, new bus drive, demo existing maintenance, transportation, District office buildings and replace with parking lots, OTMS parking and circle drive)
    • Resurface parking and drives on main campus east of Indian Lane  (Career Center, OTMS)
    • Begin construction of new gym at the high school
    • Kitchen renovations at Blue Hills, Buckner, Fire Prairie and OTMS


    Summer 2023

    • Complete new gym at the high school
    • High school band room expansion and remodel
    • Kitchen renovations at Elm Grove, Indian Trails, Cler-Mont  and high school
Fort Osage has placed two questions on the April 2021 ballot.  Please call 8166507000 for more information